I printed the report then with pen and ruler added the final lines.
What I didn't know was that someone saw this report and lost a month trying to make the same thing.
Bob
I'm using Microsoft Project 2007 to do a Gantt Chart. I've plotted 4 milestones on the same line by using the rollup options
to roll the subtasks to the summary and then collapsing the sub-tasks
view. But by doing so, the predecessor dependency links disappear if I
have to print the chart. Is it possible to have the dependency links to
point to their respective milestones on the summary bar itself?
Thanks